Sno. EVENT TIME LIMIT
in months from '0' date
1 Allocation 0
2 Purchase of GR 1.5
3 Bank Guarantee 3
4 Mining Lease Application 3
5 Mining Plan submission 6
6 Mining Plan approval 8
7 Previous approval application 11
8 Previous approval 11
9 Forest Clearance application 12
10 Forest Clearance 18
11 Environment Clearance 12
Application
12 Environment Clearance 18
13 Mining Lease grant 24
14 Land acquisition begin 9, 19
15 Land Acquisition 30, 36
16 Opening permission application 34, 40 for OC
46, 52  for UG
17 Opening permission grant 35, 41 for OC
4753 for UG
18 Production 36, 42 for OC
48, 54 for UG
19 Reaching Rated Capacity