Sl.No. |
EVENT |
TIME LIMIT IN
MONTHS (FROM THE DATE
OF ALLOCATION) |
|
1. |
PROSPECTING LICENSE |
3 |
|
2. |
COMPLETION OF EXPLORATION AND PREPARATION OF GEOLOGICAL REPORT (GR) |
27 |
|
|
EVENTS AFTER PREPARATION OF GR |
TIME LIMIT IN MONTHS AFTER PREPARATION OF GR |
|
3 |
MINING LEASE APPLICATION |
3 |
|
4 |
SUBMISSION OF MINING PLAN |
6 |
|
5 |
MINING PLAN APPROVAL |
8 |
|
6 |
PREVIOUS APPROVAL APPLICATION |
11 |
|
7 |
PREVIOUS APPROVAL |
11 |
|
8 |
FOREST CLEARANCE APPLICATION |
12 |
|
9 |
ENVIRONMENT CLEARANCE |
18 |
|
10 |
GRANT OF MINING LEASE |
24 |
|
11 |
LAND ACQUISITION BEGIN |
9, 19 |
|
12 |
LAND ACQUISITION |
30, 36 |
|
13 |
OPENING PERMISSION APPLICATION |
34, 40 (FOR OC) 46, 52 (FOR UG) |
|
14 |
GRANT OF OPENING PERMISSION |
35, 41 (FOR OC) 47 , 53 ( FOR UG) |
|
15 |
PRODUCTION |
36, 42 (FOR OC) 48, 54 (FOR UG) |
|
16 |
REACHING RATED CAPACITY |
|