MILESTONES CHART FOR UN-EXPLORED BLOCK

 

Sl.No.

EVENT

TIME LIMIT IN MONTHS

(FROM THE DATE OF ALLOCATION)

1.

PROSPECTING LICENSE

3

 

2.

COMPLETION OF EXPLORATION AND PREPARATION OF GEOLOGICAL REPORT (GR)

27

 

EVENTS AFTER PREPARATION OF GR

TIME LIMIT IN MONTHS

AFTER PREPARATION OF GR

3

MINING LEASE APPLICATION

3

 

4

SUBMISSION OF MINING PLAN

6

 

5

MINING PLAN APPROVAL

8

 

6

PREVIOUS APPROVAL APPLICATION

11

 

7

PREVIOUS APPROVAL

11

 

8

FOREST CLEARANCE APPLICATION

12

 

9

ENVIRONMENT CLEARANCE

18

 

10

 GRANT OF MINING LEASE

24

 

11

LAND ACQUISITION BEGIN

9, 19

 

12

LAND ACQUISITION

30, 36

 

13

OPENING PERMISSION APPLICATION

34, 40 (FOR OC)

46, 52 (FOR UG)

 

14

GRANT OF OPENING PERMISSION

35, 41 (FOR OC)

47 , 53 ( FOR UG)

 

15

PRODUCTION

36, 42 (FOR OC)

48, 54 (FOR UG)

 

16

REACHING RATED CAPACITY